Open Access Open Access  Restricted Access Subscription Access

Lean Implementation on Piston Manufacturing Line-4 for Better Productivity Improvement

Raveesh. T, Aravinda. T

Abstract


In this study mainly focus on improving the productivity of the Line-4 machining line at FEDERAL MOGUL GOETZE INDIA LIMITED, yelahanka, Bangalore. it is found that  Setting change over time is the major problem And Rejection rate of piston is high. These two losses will affect productivity. In order to overcome this problem implementation of SMED technique, variance analysis and DOE Using Taguchi method. SMED technique is one of the lean tools used for the reducing the setup time and to improve productivity. SMED technique was implemented on the bottleneck machine of the Line-4 machining line and calculated the setup time before and after the implementation of SMED technique. The SMED results show the significant reduction of setup time about of about 71 minutes was saved for each changeover. In this study variance analysis and DOE Using Taguchi method used to analyzing the factors affecting the rejection of piston due to variation of Skirt diameter and the better optimized variables are suggested to the management. MINITAB 17 Quality Software was used to perform variance test and DOE Using Taguchi method which provided an easy and simple way of analyzing. The variance analysis conducted indicated that feed has no effect on skirt diameter. The DOE using Taguchi method performed concluded that the Fixture Seat Diameter had a significant effect on skirt diameter. And also various action plans was implemented. The implementation of lean methodologies, the total manufacturing cost, waste and quality is achieved there by increasing the productivity. 


Full Text:

PDF

References


Amith S, Nagaraj P M, Srinivas Rao, Vijay Kumar, Overall Equipment Effectiveness Improvement of Piston Manufacturing Using SMED and DOE. IJIRSET . 2015; 4(6).

Mohammed Viqar Nadaf Pinjar, Dr. Shivakumar S, Dr. G V Patil. Productivity Improvement through Single Minite Exchange of Die (SMED)Technique. 2015; 5: ISSN 2250-3153.

Shekhar Sahu, Lakhan Patidar, Pradeep Kumar Sonl, 5S Transfusion to Overall Equipment Effectiveness for Enhancing Manufacturing Productivity, IRJET. 2015; 2(7).

m. Kumar, j. Antony, r. k. Singh, m. k. Tiwari and d. Perry. Implementing the Lean Sigma framework in an Indian SME: a case study. Production Planning & Control. 2006; 17(4).

Quazi T Z, Pratik More, Vipul Sonawane. A Case Study of Taguchi Method in the Optimization of Turning Parameters. IJETAE. 2013; 3(2): ISSN 2250-2459.

Dong-Woo Kim, Myeong-Woo Cho, Tae-Il Seo and Eung-Sug Lee. Application of Design of Experiment Method for Thrust Force Minimization in Step-feed Micro Drilling. ISSN 1424-8220 © 2008 by MDPI.

Ashwini.A, Avinash. Rejection Analysis in Piston Manufacturing Unit. IJIRSET. 2015; 4(3).

Quality Engineering Using Robust Design by Madhava S. Phadke

Quality Control and Piston Manufacturing Manual of FMGL.

Piston Defects Codes Manual of FMGL.

Mathews and Paul G, Design of experiments with MINITAB. 2014.


Refbacks